§ 31-284. Conformance with public improvements.  


Latest version.
  • Whenever by reasons of widening or straightening of streets, water or sewer line projects, or any other public works projects, (e.g., install or improve storm drains, water lines, sewer lines, etc.) it shall be deemed necessary by the governing body of the city to remove, alter, change, adapt or relocate the underground or overhead facilities to another part of the right-of-way, such alteration shall be made by the owner of the facilities at their expense within the time limits set by the city engineer working in conjunction with the owner of the facilities, or if no time frame can be agreed upon, within ninety (90) days from the day the notice was sent to make the alterations. Facilities not moved after ninety (90) days or within the approved schedule, as same may be extended from time to time, shall be deemed abandoned after thirty (30) days notice.

(Ord. No. 00-048, § 2 (part), 6-8-00)