  • The point of attachment on a building shall be installed so that the bottom of the drip loop, from the point of attachment to the service head, is no less than ten (10) or more than twenty-five (25) feet above grade unless special permission is required for other clearances. On permanent meter pole installations, the bottom of the drip loop shall have twelve (12) feet clearance.

(Code 1960, § 27-36(f); Ord. No. 85-67, § 12, 9-26-85)